Timeline

Anticipated Finish: February 2021

 Next Milestone: Completion of Podium - August 2019

AUGUST 2019 - Retail Podium formwork nearing completion - two slabs pours to complete roof

 

JAN 2019 - Garage formwork is approaching Lower Floor Grade

 

Excavation almost complete and the crane erected and certified. Starting to pour footings and install blindside waterproofing.

 

Excavation to be completed in July 2018


 

General Work Hours

Weekdays: 6am - 7pm (subject to concrete pouring days, which may end later)

Saturdays: 7am - 7pm